top of page

Water Reservoir Access Platform

Our Client had identified an on-going safety issue for their operators who were required to access the Spillway Wall for routine maintenance. Having to walk over a rocky and steep terrain followed by a slippery embankment to access to top of the wall provided an imminent risk of slips, trips and falls. We were requested to design and engineer a safer alternative that also aesthetically blended into the natural landscape.

Project Highlights

  • Delivery of a walkway that enhanced the natural environment that it was installed in.

  • Being able to adapt and problem solve design issues that were encountered on-site due to unforeseen natural impacts

  • Handing back the area in a healthier environmental condition than when works commenced

Services Provided

  • Collaboration with key-stakeholders to conceptualise a solution that was not only practicable but visually appealing

  • Design and engineering of a suitable walkway that embraced the natural surroundings of the area

  • On-site installation of the walkway ensuring that design drawings were adhered to in order to comply with Australian Standards

  • Provision of on-site amenities to cater for crews working in a remote area

  • Assure the protection of native flora and fauna by providing revegetation where existing had been disturbed

Services Provided

  • Assessment of the condition of the deteriorated carpark and surrounding areas.

  • Collaboration with our client to develop a Request for Quotation (RFQ) for the rectification works, providing expert advice and recommendations on the best approach to address the issues within budget and time constraints. 

  • Implementation of safety measures by cordoning off the affected areas to prevent public access during the works.

  • Carrying out the necessary resurfacing and repairs to the carpark and other high-traffic areas, ensuring a safe and functional environment for the public until the larger capital project is completed. 

Related Case Studies

Rawson Crater Lake

Power Station Building Upgrades

Surrey Hill Valve Pit

Challenges

  • Difficult access to transport materials and equipment throughout the worksite as the crew were combating the slips, trips and falls hazards that the project was designed to eliminate

  • Footing locations were constantly adjusted throughout the project due to terrain and rock interference with the footings which required constant problem-solving and adjustments to original design

  • Being in such a remote location required additional logistics and planning, whilst also being constantly on guard for snakes and other hazards

Outcome

The client was delighted with the outcome, as the access platform was successfully integrated into the natural landscape, maintaining both functionality and aesthetic harmony with the surroundings. 

 

The slips, trips and fall hazards had successfully been eliminated and provided a practicable solution for operators to deliver their on-going maintenance of the Spillway Wall.

 

There was also a great deal of pride and satisfaction from our staff upon the completion and handover of the project.

Return to Case Studies
bottom of page