High Voltage Room Door Replacement
The fire door to a high voltage building was identified as being riddled with white ants and was no longer structurally sound. We were tasked with the replacement of the door with a specifically designed fireproof door that was treated to prevent further white ant infiltrations.
Project Highlights
-
Ensuring a safe and successful outcome for the client
-
Guaranteeing compliance is achieved for the clients and operators onsite.
Challenges
-
Coordinating safely and efficiently with another contractor undertaking simultaneous landscaping works presented logistical challenges.
-
Accurately setting fence heights and alignments based on provided drawings was critical, as the fence needed to accommodate a future path installation.
Services Provided
-
Production of tank specific ITP’s to ensure that the recommended remediation works are undertaken as intended.
-
Roof sealing to provide waterproofing including the application of silicon’s or similar waterproofing agents, filling of any perforations or identified gaps in roof structures, replacement of roof sheet metal, replacement of roof screws or similar tie downs, replacement of covers
-
Steel plate floor patching via approved AS4020:2018 potable water safe epoxy product and installation methodology
-
Replacement of gaskets used to seal hatches, doorways, etc
-
We made structural repairs to high level structural supports repairing the structural bracing at high levels
Outcome
The Council and client were highly satisfied with the completed installation, which met all project requirements and expectations. The final site inspection was completed without any issues, and no punch list items were raised. Overall, the project was completed successfully and received positive feedback from all stakeholders.
Services Provided
-
Assessment of the condition of the deteriorated carpark and surrounding areas.
-
Collaboration with our client to develop a Request for Quotation (RFQ) for the rectification works, providing expert advice and recommendations on the best approach to address the issues within budget and time constraints.
-
Implementation of safety measures by cordoning off the affected areas to prevent public access during the works.
-
Carrying out the necessary resurfacing and repairs to the carpark and other high-traffic areas, ensuring a safe and functional environment for the public until the larger capital project is completed.