The client faced serious safety concerns due to outdated ladders on-site, which posed a fall risk of over 2 meters and raised worker complaints. They needed an immediate and practical solution to ensure safe access for tower crews, as well as a long-term fix that met updated safety standards. We responded by first installing temporary scaffold staircases, then delivering a redesigned access system with reduced platform spacing, rest areas, and angled ladders. Additionally, the client required stronger site security following repeated break-ins, which we addressed by installing a high-security perimeter fence.

Project Highlights

  • Precision Installation: A standout aspect of the project was the high level of accuracy achieved during installation. The fully assembled structure was only millimetres off the intended specifications.
    Quality and Craftsmanship: This outcome highlights the team's meticulous attention to detail and strong commitment to delivering exceptional, high-quality results.

Services Provided

  • Fabrication

  • Excavation

  • Concreting

  • Fence Installation including vehicle access gates

  • Crane Operation (delivery partner)

  • EWP Operation

  • Project Management and Logistics

Services Provided

  • Assessment of the condition of the deteriorated carpark and surrounding areas.

  • Collaboration with our client to develop a Request for Quotation (RFQ) for the rectification works, providing expert advice and recommendations on the best approach to address the issues within budget and time constraints. 

  • Implementation of safety measures by cordoning off the affected areas to prevent public access during the works.

  • Carrying out the necessary resurfacing and repairs to the carpark and other high-traffic areas, ensuring a safe and functional environment for the public until the larger capital project is completed. 

Related Case Studies

Water Reservoir Access Platform

Read More

Winneke Treatment Plant Security Upgrades

Read More

Rawson Crater Lake

Read More

Challenges

  • Logistical challenges due to limited access. The team had to coordinate the use of transport pilots and implement temporary road closures to navigate narrow routes. This required meticulous planning and highlighted the complexity of the project, as well as the team’s ability to adapt and problem-solve in real time. Delivering the pre-fabricated ladder system to the site posed significant l

  • The project was carried out under highly variable weather conditions, including snow, rain, and extreme heat. These fluctuations demanded flexible scheduling and careful execution at every stage to maintain safety and productivity. The team’s resilience and ability to adapt to unpredictable environmental factors were critical to keeping the project on track.

Outcome

The successful completion of this project stands as a testament to the team's unwavering dedication, precision, and adaptability, by addressing worker safety concerns. A standout achievement was the exceptional accuracy of the structure, which, upon completion, was just millimetres off from its intended specifications, reflecting the team's attention to detail and technical expertise. The culmination of these efforts resulted in a comprehensive and impactful upgrade to the tower, prioritizing the well-being of its operators and the integrity of the site. This project truly exemplifies the team's commitment to excellence in every facet.